Unit 5 Demolition Work:
WORKS COMMENCING: MONDAY 20TH APRIL 2020
EXPECTED COMPLETION: 5TH JUNE 2020
The works comprise the demolition of unit 5 which is located to the south of the site. The site area is fenced off and plant and lorry movements will be kept to a minimum. The majority f works will be internal and will comprise low noise levels. The demolition will be carried out in a controlled modular sequence after the internal works are complete. Skips will be placed close the the works and removal will be carried out efficiently. The concrete floor slab will be retained avoiding heavy breaking and noisy operations.
Arlington Access Improvement – S.278 Works
WORKS COMMENCING MONDAY 4TH MAY 2020
EXPECTED COMPLETION 19TH JUNE 2020
The works will construct a new vehicular access off Campbell Road, creating improved visibility splays and vehicle movement. The will include enhanced construction to the bellmouth and kerning to the footway.
Traffic management will be in place for approx. 2 weeks from the 18th May to mitigate any public or personnel risk, this will include 2 was traffic lights.
All efforts will be made to reduce inconvenience and disruption.